| Emergency | Closed | 1F | Jan 5, 2011 | PAINT/PLASTER · CEILINGThe Department of Housing Preservation and Development inspected the following conditions. Violations were issued. Information about specific violations is available at www.nyc.gov/hpd |
| Non-emergency | Closed | 37E | Jan 3, 2011 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development inspected the following conditions. No violations were issued. The complaint has been closed. |
| Non-emergency | Closed | 30G | Jan 3, 2011 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development was not able to gain access to inspect the following conditions. The complaint has been closed. If the condition still exists, please file a new complaint. |
| Emergency | Closed | 31H | Dec 15, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development was not able to gain access to inspect the following conditions. The complaint has been closed. If the condition still exists, please file a new complaint. |
| Non-emergency | Closed | 1H | Dec 15, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development inspected the following conditions. No violations were issued. The complaint has been closed. |
| Non-emergency | Closed | 1H | Dec 15, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development inspected the following conditions. No violations were issued. The complaint has been closed. |
| Non-emergency | Closed | 1H | Dec 15, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development inspected the following conditions. No violations were issued. The complaint has been closed. |
| Emergency | Closed | 1H | Dec 15, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development inspected the following conditions. No violations were issued. The complaint has been closed. |
| Emergency | Closed | 1H | Dec 15, 2010 | PAINT/PLASTER · CEILINGThe Department of Housing Preservation and Development inspected the following conditions. No violations were issued. The complaint has been closed. |
| Non-emergency | Closed | 1H | Dec 15, 2010 | PAINT/PLASTER · CEILINGThe Department of Housing Preservation and Development inspected the following conditions. No violations were issued. The complaint has been closed. |
| Non-emergency | Closed | 1H | Dec 15, 2010 | PAINT/PLASTER · CEILINGThe Department of Housing Preservation and Development inspected the following conditions. No violations were issued. The complaint has been closed. |
| Non-emergency | Closed | 1H | Dec 15, 2010 | PAINT/PLASTER · CEILINGThe Department of Housing Preservation and Development inspected the following conditions. No violations were issued. The complaint has been closed. |
| Non-emergency | Closed | 1H | Dec 15, 2010 | PAINT/PLASTER · CEILINGThe Department of Housing Preservation and Development inspected the following conditions. Violations were issued. Information about specific violations is available at www.nyc.gov/hpd |
| Emergency | Closed | 1H | Dec 15, 2010 | PAINT/PLASTER · CEILINGThe Department of Housing Preservation and Development inspected the following conditions. No violations were issued. The complaint has been closed. |
| Emergency | Closed | 31H | Dec 15, 2010 | PAINT/PLASTER · CEILINGThe Department of Housing Preservation and Development was not able to gain access to inspect the following conditions. The complaint has been closed. If the condition still exists, please file a new complaint. |
| Emergency | Closed | 31H | Dec 15, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development was not able to gain access to inspect the following conditions. The complaint has been closed. If the condition still exists, please file a new complaint. |
| Non-emergency | Closed | 33H | Nov 29, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development inspected the following conditions. No violations were issued. The complaint has been closed. |
| Non-emergency | Closed | 33H | Nov 29, 2010 | PAINT/PLASTER · CEILINGThe Department of Housing Preservation and Development inspected the following conditions. No violations were issued. The complaint has been closed. |
| Emergency | Closed | 13K | Nov 24, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development inspected the following conditions. No violations were issued. The complaint has been closed. |
| Non-emergency | Closed | 9B | Nov 12, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development inspected the following conditions. Violations were issued. Information about specific violations is available at www.nyc.gov/hpd |
| Non-emergency | Closed | 9B | Nov 12, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development inspected the following conditions. Violations were issued. Information about specific violations is available at www.nyc.gov/hpd |
| Emergency | Closed | 18F | Nov 10, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development inspected the following conditions. No violations were issued. The complaint has been closed. |
| Non-emergency | Closed | 18F | Nov 10, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development inspected the following conditions. No violations were issued. The complaint has been closed. |
| Emergency | Closed | 22C | Oct 26, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development was not able to gain access to inspect the following conditions. The complaint has been closed. If the condition still exists, please file a new complaint. |
| Non-emergency | Closed | 37E | Oct 12, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development inspected the following conditions. Violations were issued. Information about specific violations is available at www.nyc.gov/hpd |
| Non-emergency | Closed | 37E | Oct 8, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development contacted an occupant of the apartment and verified that the following conditions were corrected. The complaint has been closed. If the condition still exists, please file a new complaint. |
| Non-emergency | Closed | 22A | Oct 4, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development inspected the following conditions. Violations were issued. Information about specific violations is available at www.nyc.gov/hpd |
| Emergency | Closed | 37E | Oct 2, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development was not able to gain access to inspect the following conditions. The complaint has been closed. If the condition still exists, please file a new complaint. |
| Non-emergency | Closed | 19-G | Sep 23, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development inspected the following conditions. Violations were issued. Information about specific violations is available at www.nyc.gov/hpd |
| Non-emergency | Closed | 19-G | Sep 23, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development inspected the following conditions. No violations were issued. The complaint has been closed. |
| Non-emergency | Closed | 19-G | Sep 23, 2010 | PAINT/PLASTER · CEILINGThe Department of Housing Preservation and Development inspected the following conditions. Violations were issued. Information about specific violations is available at www.nyc.gov/hpd |
| Non-emergency | Closed | 33H | Sep 13, 2010 | PAINT/PLASTER · CEILINGThe Department of Housing Preservation and Development inspected the following conditions. Violations were issued. Information about specific violations is available at www.nyc.gov/hpd |
| Non-emergency | Closed | 35D | Aug 30, 2010 | PAINT/PLASTER · CEILINGThe Department of Housing Preservation and Development inspected the following conditions. No violations were issued. The complaint has been closed. |
| Non-emergency | Closed | 10G | Aug 15, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development inspected the following conditions. No violations were issued. The complaint has been closed. |
| Non-emergency | Closed | 10G | Aug 15, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development inspected the following conditions. No violations were issued. The complaint has been closed. |
| Non-emergency | Closed | 28E | Aug 9, 2010 | PAINT/PLASTER · CEILINGThe Department of Housing Preservation and Development inspected the following conditions. Violations were issued. Information about specific violations is available at www.nyc.gov/hpd |
| Non-emergency | Closed | 28E | Jul 23, 2010 | PAINT/PLASTER · CEILINGThe Department of Housing Preservation and Development inspected the following conditions. Violations were issued. Information about specific violations is available at www.nyc.gov/hpd |
| Non-emergency | Closed | 28E | Jul 23, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development inspected the following conditions. Violations were issued. Information about specific violations is available at www.nyc.gov/hpd |
| Non-emergency | Closed | 14C | Jul 9, 2010 | PAINT/PLASTER · CEILINGThe Department of Housing Preservation and Development was not able to gain access to inspect the following conditions. The complaint has been closed. If the condition still exists, please file a new complaint. |
| Non-emergency | Closed | 14C | Jul 9, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development was not able to gain access to inspect the following conditions. The complaint has been closed. If the condition still exists, please file a new complaint. |
| Non-emergency | Closed | 14C | Jul 9, 2010 | PAINT/PLASTER · CEILINGThe Department of Housing Preservation and Development was not able to gain access to inspect the following conditions. The complaint has been closed. If the condition still exists, please file a new complaint. |
| Emergency | Closed | 17A | Jun 13, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development inspected the following conditions. No violations were issued. The complaint has been closed. |
| Non-emergency | Closed | 26H | Jun 8, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development inspected the following conditions. No violations were issued. The complaint has been closed. |
| Non-emergency | Closed | 13K | May 10, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development inspected the following conditions. No violations were issued. The complaint has been closed. |
| Non-emergency | Closed | 13K | May 10, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development inspected the following conditions. No violations were issued. The complaint has been closed. |
| Emergency | Closed | 13K | May 10, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development inspected the following conditions. No violations were issued. The complaint has been closed. |
| Non-emergency | Closed | 1H | May 8, 2010 | PAINT/PLASTER · CEILINGThe Department of Housing Preservation and Development was not able to gain access to inspect the following conditions. The complaint has been closed. If the condition still exists, please file a new complaint. |
| Emergency | Closed | 1H | May 8, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development was not able to gain access to inspect the following conditions. The complaint has been closed. If the condition still exists, please file a new complaint. |
| Non-emergency | Closed | 1H | May 8, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development was not able to gain access to inspect the following conditions. The complaint has been closed. If the condition still exists, please file a new complaint. |
| Non-emergency | Closed | 1H | Apr 21, 2010 | PAINT/PLASTER · WALLThe Department of Housing Preservation and Development inspected the following conditions. No violations were issued. The complaint has been closed. |